Home    
 CPUC Home
 Site Resources
 wedge graphic  Public Process
 wedge graphic  A.04-11-011 Proceeding Link
 wedge graphic  History
 wedge graphic  Contact Info
 wedge graphic  Related Links
View PG&E's Proponents Environmental Assessment (PEA)  PEA
(Proponents Environmental Assessment)
 CEQA Documents
View the Notice of Intent  NOI
View the Draft Mitigated Negative Declaration  Draft MND
 View the Notice of Availability  NOA
 View the Final Mitigated Negative Declartion  Final MND
 View the Notice of Determination  NOD
 Acrobat(tm) Info
 Note: all documents on this site are available in Adobe AcrobatTM format only. To view these documents you will need to have the free Adobe Acrobat Reader (version 7 or greater) installed on your computer. Using Acrobat Reader you may view document files here on-line or download them for off line viewing or printing.
Click on the link below to jump to Adobe's website to obtain a free copy of their reader.
 wedge graphic  Get Acrobat Reader
PG&E's Lakeville Sonoma 115 kV Transmission Line Project (A.04-11-011)

PG&E Lakeville-Sonoma 115 kV Transmission Line Project

Project History

On June 29, 2006 the Commission adopted the MND. This proceeding is closed.
Publication of a Final Mitigated Negative Declaration (FMND)

The Commission has published a final Mitigated Negative Declaration (FMND) on March 23, 2006, SCH Number 2005122042. View the Notice of Availability for the FMND.

Public Information Meeting

The CPUC held a public information meeting on January 4, 2006 at the Sonoma Valley Regional Library Forum Room, between 6:30 and 8:30pm.

Publication of a Draft Mitigated Negative Declaration (DMND)

On December 9, 2005 a Draft MND for PG&E’s Lakeville-Sonoma 115 kV Transmission Line Project A.04-11-011 was published by the CPUC. The comment period for the Draft MND ended on January 9, 2006. The Draft MND can be viewed by clicking on the link in the sidebar on this page.

On April 13, 2005, PG&E filed an ammendment to its Application. This ammendment revised several aspects of the proposed project. To view this ammendment click here [pdf, 1.6mb]. To view the full color version of the figures included in the ammendment click here [pdf, 27mb]. Following this filing, several intervenors filed protests to this amended Application. PG&E has filed a response to the intervenors.

On November 17, 2004, PG&E filed an Application, (A.04-11-011), for a Permit to Construct (PTC), including a Proponent's Environmental Assessment (PEA). The proposed project consists of upgrading an approximately 7.2 mile 115 kV transmission line and modifications to PG&E's Lakeville and Sonoma substations both located in sothern Sonoma County. Following this filing, several intervenors filed protests to this application. PG&E has filed a response to the intervenors. PG&E's PEA may be viewed by clicking on the PEA link on the left side of this page.